Dam & Spillway Project

Dam & Spillway Committee: Bill Cole, Pat McAnany, Dave McCullagh, Annie Noland, Win Zoellner

The City of Lake Quivira and Olsson Engineering have developed a preliminary design plan for the replacement of the Northwest spillway (downstream side).

The spillway features:

  • Concrete channel that transitions from a height of 10 feet (at the bridge end) to 6 feet (at the spillway end and before the waterfall).
  • Fencing on the top of the spillway for safety purposes that coordinates aesthetically with existing fencing.
  • Stonework repair/replacement on both sides of the road.
  • Bridge sandblasting and painting
  • Hardscaping (colored/pressed concrete) on the area between the new channel and stone wall.
  • Landscaping on the west side of the spillway up to Renner Road.
  • Moving existing power pole on north west corner (discussions in process with Evergy).

Preliminary timeline for the project:

  • Final engineering approval by Council: 07/10/2023
  • Submit plans to the State: 07/10/2023
  • Promote projects to potential contractors: 07/11/2023
  • Bid Process begins: 08/04/2023
  • Final bid awarded and signed: 08/31/2023
  • Final response to the State: 09/15/2023
  • Gather bids and select contractors: 08/15/2023 - 09/15/2023
  • Lower lake to prepare for work: 09/25/2023
  • Work begins: 10/01/2023 - 12/31/2023
  • Stonework and landscape work: 01/01/2024 - 04/15/2023