Dam & Spillway Project

Working...

Ajax Loading Image

 

Project informaiton

 

Dam/Spillway Project

 

The City of Lake Quivira and Olsson Engineering have developed a preliminary design plan for the replacement of the Northwest spillway (downstream side).  The spillway features:

 

  • Concrete channel that transitions from a height of 10 feet (at the bridge end) to 6 feet (at the spillway end and before the waterfall)
  • Fencing on the top of the spillway for safety purposes that coordinates aesthetically with existing fencing
  • Stonework repair/replacement on both sides of the road
  • Bridge sandblasting and painting
  • Hardscaping (colored/pressed concrete) on the area between the new channel and stone wall.
  • Landscaping on the west side of the spillway up to Renner Road
  • Moving existing power pole on north west corner (discussions in process with Evergy)

 

Preliminary timeline for the project:

 

  • Final engineering approval by Council – 7/10/23
  • Submit plans to State – 7/10/23
  • Promote project to potential contractors – 7/11/23
  • Bid Process Begins – 8/4/23
  • Final Bid Awarded and Signed – 8/31/23
  • Final response to the State – 9/15/23
  • Gather bids and select contractors – 8/15/23 - 9/15/23
  • Lower lake to prepare for work – 9/25/23
  • Work begins – 10/1/23 – 12/31/23
  • Stonework and landscape work – 1/1/24 – 4/15/23 

Click on links below to view final plans and design report:

Final Plans 

Design Report